Projects & case studies

Proof, not promises.

Refilling stations, hospitals, telecom towers, offices and factories across Nigeria already run on Pulita equipment.

100+

Nigerian projects in our portfolio

10+

States: Lagos, Abuja (FCT), Ogun, Osun, Kano, Rivers, Akwa Ibom, Oyo…

3.6MW

Largest single site (Uyo hotel)

20kVA+

From telecom sites to power plants

Case study

Burger King Abeokuta: a green restaurant with zero diesel.

How an 80 kVA Pulita LPG generator helped Burger King Nigeria open its first green restaurant in Abeokuta, Ogun State.

80 kVAPulita LPG generator set
0 Ldiesel used on site
~54%lower fuel cost vs diesel*

The challenge

Burger King Nigeria wanted its Abeokuta outlet to set a new standard for sustainable restaurant design. The restaurant had to run kitchens, cold rooms and air-conditioning every day without the diesel generators that power most Nigerian businesses, and without the cost, fumes and noise that come with them.

The solution

Pulita supplied an 80 kVA LPG generator set sized for the restaurant’s full load. Our Nigerian engineers installed and commissioned it on site, connecting it to the LPG supply and setting it up for reliable daily operation. LPG is widely available across Ogun State, so refuelling is simple, and lean-combustion technology gets more electricity from every kilogram of gas.

The result

At the launch, Burger King Nigeria described the Abeokuta outlet as its first green restaurant: built from recycled shipping containers, powered by a gas generator, cooled by gas air-conditioning and running with zero diesel. The site became the chain’s 23rd outlet in Nigeria and a visible showcase of what gas power can do for commercial operators.

*Estimate from Pulita’s LPG vs diesel reference data (100 kW, ₦950/kg LPG vs ₦2,000/L diesel). Actual savings depend on load and local fuel prices.

Case study · Refuelling

Kubwa, Abuja: a CNG refilling station without a pipeline.

How Pulita compressors and a mobile refuelling unit (MRU) put CNG refuelling in Kubwa, Abuja, for vehicles, buses, trucks and gas generators.

MRUcontainerized refuelling unit
250 barcompression & dispensing
3 usesvehicles, buses & trucks, generators

The challenge

Demand for CNG in Abuja is growing faster than traditional stations can be built. A conventional station needs a pipeline connection, major civil works and a long build. The client needed refuelling capacity on site quickly.

The solution

Pulita supplied CNG compressors and a containerized mobile refuelling unit (MRU) with its storage cascade and dispenser. The client buys gas from Pulita’s partner gas suppliers, so it could open a refilling business without building its own gas supply.

The result

The Kubwa station now refills CNG vehicles, buses and trucks, and supplies gas to power generators. Because the MRU is containerized, it can be relocated or expanded as demand grows.

Case study · Industrial

Kano plastics factory: 750 kVA of CNG power, 24 hours a day.

How a Pulita 750 kVA CNG generator set keeps a plastics factory in Kano State running around the clock.

750 kVAPulita CNG generator set
24 h/daycontinuous operation
~77%lower fuel cost vs diesel*

The challenge

Plastics production runs day and night, and the machines need steady power to avoid wasted batches. Running a large diesel generator around the clock made fuel the factory’s biggest operating cost.

The solution

Pulita supplied a containerized 750 kVA CNG generator set, with the gas supply line, buffer tank and pressure-regulating cabinet that feed it clean gas at the right pressure.

The result

The generator set now powers the factory 24 hours a day on natural gas instead of diesel.

*Estimate from Pulita’s CNG vs diesel reference data. Actual savings depend on load and local fuel prices.

Sectors we power

Built for the way Nigeria works.

Hospitals

Clean, quiet, 24/7 power for critical care, from 300 to 450 kVA and beyond.

Telecom

Compact 25 kVA CNG sets for towers, with no diesel to steal.

Gas stations

MRUs, daughter stations and station power, delivered turnkey.

Commercial & industry

Offices, restaurants, water factories and plants cutting energy costs by 54–77%.